Village of Camden
Sidewalk Project – South Elm St. & South Fayette
St. Neighborhood
Contact Person: Robert Sauer, Mayor-Village of Camden,
245-0560
Karl Keil, Jr., Supt. of Public Works-Village of
Camden, 245-0560
Award Amount: $20,000
Project Description:
The Village of Camden will utilize funding for a concrete sidewalk
installation project. The new sidewalk will be installed in the Village
right of way along the South Elm Street and South Fayette Street blocks
between Liberty Street and Oswego Street. The Village of Camden Department
of Public Works will provide labor for the project.
The project purpose is to provide support for a
low-income neighborhood that has sidewalk disrepair and non-existing
pedestrian walkways causing unsafe pedestrian thoroughfares. The project
will provide safe pedestrian walkways especially for the children and the
handicapped in the close proximity of Camden Elementary and Camden High
School.
Timeline:
Commence work – May 1, 2000
Project Completion – September 30, 2000 |